Posts Tagged ‘Completed’
Two Weeks, Twenty Feet
I returned from vacation and the excavator was gone. So was about, say 24,000 cubic sq. feet of dirt from the south half of the Koons site. Whatever it is, lets say the excavation phase is done. For joy… though I’m saving Beethoveen’s 9th for when the 21st Rd bus stop is moved to its new home… to the east of…21st Rd. I noticed concrete barricades were placed around the garage and FS3 site today so construction must be ready to start. Actually it has in small ways, but that’s another post for another day. For now here are the “final” excavation pictures for the Koons Garage. Enjoy and think back to when you first heard about the notion of a Koons Garage in 2005. Crazy.
North Towards Old Dominion:

South Toward Lee Hwy:

If you were wondering about those three beams, it’s not an homage to Stonehenge; it’s just a pipe stem being set:

Looking South, Close up & Deep: