Backed Up
Missed a week. Blame it on the Nats. Blame it on the iPhone 4. If you have driven by the site you’ll notice the back retaining wall has been completed. According to the June 16 county update, W-T is waiting for a wall check survey. Once completed and accepted by the county a final building permit will be issued as well as a plumbing permit. There is also an “alignment issue” between the Koons Garage and FS3 site where the “openings on the parking garage were not coordinated with the planned slope of the fire station grade.” Architects for both projects are working on a fix.